by DickoDev | Feb 5, 2024 | Construction
MILESTONES Patching/repairing all blinding leaks to raft/crane base Waterproof blanket Installing embedded element for the tower crane Installing crane base rebar Crane base pour Tower crane install & commission Patching and repairs to leaking wall blinding...
by DickoDev | Jan 5, 2024 | Construction
MILESTONES Back blinding to walls Blinding to Nortth section and perimeter Relocated the stretcher scaffold to the North Servicing of the dewatering system Chipping/cutting pile faces Digging pads and raft Digging/installing agi drains for water ingress Back blind...
by DickoDev | Dec 1, 2023 | Construction
MILESTONES Bulking slop that was dripping out of the tandems Installing agi drain lines Back blinding prep Dig pad footing SAT blinding and shotcrete...
by DickoDev | Oct 1, 2023 | Construction
MILESTONES 130t crane set up again to remove the anchor rig Drop in the 7T excavator and all our waterproofing gear Install more road plates to the footpath Install & inspect B2 waterproofing Complete all mesh & bars and prep for shotcrete Set up new...
by DickoDev | Sep 1, 2023 | Construction
MILESTONES Connected the dewatering system to the existing storm water Sprayed the capping beam Poured the top down slab which will open up access to the site Detailed the east wall and commence shotcrete prep Silt tank and pumps onsite Remove the entire hoarding and...
by DickoDev | Aug 1, 2023 | Construction
MILESTONES Install bollards and screens to High St Work/loading zone Completed B1 ground anchors Continued to modify the dewatering system in search of optimum flow Measure first waler steels and bolt locations Installed new North boundary paling fence B1 shotcrete...