Construction Update – June 2023

Construction Update – June 2023

MILESTONES Connected the dewatering system to the existing storm water Sprayed the capping beam Poured the top down slab which will open up access to the site Detailed the east wall and commence shotcrete prep Silt tank and pumps onsite...
Construction Update – May 2023

Construction Update – May 2023

MILESTONES Site establishment & amenities Dewatering Import mudstone, complete piling platform and testing Bulking out fill and prepping platform for piling stage 2  Continuing piling including the first 2 piles in the existing shop front Lifting all remaining...
Demolition Complete

Demolition Complete

Demolition has been completed and the site is clear. In preparation for Cobild starting construction early next year the parts of the existing buildings that are not being retained for their Heritage Significance have been demolished. The site is now clear for Cobild...
Builder Appointment

Builder Appointment

Welcome COBILD! The Development Team are delighted to announce that we have entered into a construction contract with Cobild. We are really excited to be working with such a quality builder who have an impeccable reputation when it comes to building luxury apartments....