MILESTONES
130t crane set up again to remove the anchor rig
Drop in the 7T excavator and all our waterproofing gear
Install more road plates to the footpath
Install & inspect B2 waterproofing
Complete all mesh & bars and prep for shotcrete
Set up new dewatering hoses and manifold
- Bulk spoils and detail
- Complete anchors
- Scaffold relocated
- Continue jetting and de-sludging the dewatering wells for the next drop