MILESTONES
Site establishment & amenities
Dewatering
Import mudstone, complete piling platform and testing
Bulking out fill and prepping platform for piling stage 2
Continuing piling including the first 2 piles in the existing shop front
Lifting all remaining pile cages onto site with the 80T crane
Setting out and commencing piles to the North boundary