MILESTONES
- Install bollards and screens to High St Work/loading zone
- Completed B1 ground anchors
- Continued to modify the dewatering system in search of optimum flow
- Measure first waler steels and bolt locations
- Installed new North boundary paling fence
- B1 shotcrete complete
- B1 ground anchors stressed
- B1 waler beam installed
- Lowered dewatering pump lines ahead of bulking to B2
- First precast sample on site