Construction Update – August 2023

Sep 1, 2023 | Construction

MILESTONES

  • Connected the dewatering system to the existing storm water
  • Sprayed the capping beam
  • Poured the top down slab which will open up access to the site
  • Detailed the east wall and commence shotcrete prep
  • Silt tank and pumps onsite
  • Remove the entire hoarding and rebuild to fit the 130T crane in the front yard (in the rain)