by DickoDev | Feb 5, 2024 | Construction
MILESTONES Patching/repairing all blinding leaks to raft/crane base Waterproof blanket Installing embedded element for the tower crane Installing crane base rebar Crane base pour Tower crane install & commission Patching and repairs to leaking wall blinding...
by DickoDev | Jan 5, 2024 | Construction
MILESTONES Back blinding to walls Blinding to Nortth section and perimeter Relocated the stretcher scaffold to the North Servicing of the dewatering system Chipping/cutting pile faces Digging pads and raft Digging/installing agi drains for water ingress Back blind...
by DickoDev | Dec 1, 2023 | Construction
MILESTONES Bulking slop that was dripping out of the tandems Installing agi drain lines Back blinding prep Dig pad footing SAT blinding and shotcrete...
by DickoDev | Nov 1, 2023 | Uncategorized
MILESTONES Load in 12T and 20T rigs Bulk 2/3 of the next drop Craned in the small anchor rig Commenced anchors Prepped site for the next scaffold rotation Commence jetting and de-sludging the dewatering wells for the next drop Final bulk and detail for the mid B3 drop...
by DickoDev | Oct 1, 2023 | Construction
MILESTONES 130t crane set up again to remove the anchor rig Drop in the 7T excavator and all our waterproofing gear Install more road plates to the footpath Install & inspect B2 waterproofing Complete all mesh & bars and prep for shotcrete Set up new...